Stage | Payment Under a Standard Payment Scheme (% of Purchase Price) |
---|---|
Upon the grant of Option to Purchase | 5% (Booking Fee) |
Upon signing of the Sale & Purchase Agreement or within 8 weeks from the Option date | 20% less Booking Fee |
Completion of foundation work | 10% |
Completion of reinforced concrete framework of unit | 10% |
Completion of partition walls of unit | 5% |
Completion of roofing/ceiling of unit | 5% |
Completion of door sub-frames/ door frames, window frames, electrical wiring, internal plastering and plumbing of unit | 5% |
Completion of car park, roads and drains serving the housing project | 5% |
Notice of Vacant Possession (TOP) | 25% |
On Completion date | 15% |
Developer: GuocoLand, Hong Leong and TID
Tenure: 99 years leasehold
Expected Date Of Vacant Possession: 01 December 2028
Expected Date Of Legal Completion: 01 December 2031
Copyright © 2022 | Lentor Hills Residences
Oops! We could not locate your form.
Oops! We could not locate your form.
Oops! We could not locate your form.
Oops! We could not locate your form.
Oops! We could not locate your form.
Oops! We could not locate your form.
Oops! We could not locate your form.
Oops! We could not locate your form.